Summary
Management framed the call around executing its copper-and-gold strategy, with KFM Phase II progress and acquired-asset operations emphasized over near-term price forecasts.
- KFM Phase II remains on schedule for 2027, while Ecuador’s Odin gold mine is planned for 2029.
- Brazil gold-mine integration was described as smooth, with China-Brazil management credited for improving mining, processing and smelting efficiency.
- Copper prices were characterized as driven recently by macro factors; management offered no 2027 price outlook.
Guidance
- 2026 copper production 760,000–820,000 tons
- 2026 gold production 6–8 tons, all from Brazilian projects
- KFM Phase II planned start-up 2027
- KFM Phase II copper increment 100,000 tons annual average
- Ecuador gold mine planned start-up 2029
What analysts pressed on
- 01Congo cobalt quotas: policy is clear through 2027, but future changes are uncertain; management will maintain government communication.
- 02Capital returns: management said it balances business development and shareholder cash returns, but gave no buyback or dividend targets.
- 03Copper growth projects: KFM Phase II is scheduled for 2027; TFM Phase III plans were not quantified and deferred to announcements.
- 04Gold growth: Odin is in planning for 2029, but management declined to provide AISC or project capacity details.
- 05Copper pricing: recent moves were attributed mainly to macro factors; management gave no 2027 price forecast.
Notable disclosures
- Congo cobalt export quotas are clear through 2027, but management said future policy changes remain uncertain.
- Cobalt inventory is measured at production cost; management expects no impairment and described storage costs as low.
- KFM’s acid plant is under construction and expected to operate next year, reducing purchased-acid requirements.
- Management said KFM Phase II adds 100,000 tons of annual-average copper output, while giving no TFM Phase III schedule.
Risks raised
- Congo cobalt export quotas remain in force through 2027, with no clarity on subsequent policy changes.
- Rising sulfuric acid prices and other auxiliary-material costs were raised as pressure on copper production costs.
- Investment cash outflow and construction spending have increased; management did not quantify the effect on dividends or buybacks.
- Copper prices have recently fluctuated with macro factors, while cobalt prices and quota restrictions were raised as investor concerns.
Tone: Mildly positive 0.25
Tone was constructive on project execution and resource potential, but management avoided quantifying returns, future policy impacts and some project plans.
Who spoke
Company
- XU HUIBoard Secretary, CMOC GROUP
Full transcript
Analyst questions are marked with a bar. Timestamps are into the recording.
Prepared remarks
ModeratorSSE Roadshow Center
Ladies and gentlemen, investors and netizens, hello! Welcome to the performance presentation of Luoyang Molybdenum for the third quarter of 2026. This activity is sponsored by Luoyang Luanchuan Molybdenum Industry Group Co., Ltd. and supported by the network platform provided by Shanghai Stock Exchange Information Network Co., Ltd. Thank you for your attention and participation. On October 24, Luoyang Luanchuan Molybdenum Industry Group Co., Ltd. published the Third Quarter Report of 2026. Investors can log on the website of Shanghai Stock Exchange (http://www.sse.com.cn/) or this platform (https://roadshow.sseinfo.com/).
View related announcements. In order to facilitate investors to have a more comprehensive and in-depth understanding of the company's operating results and financial situation in the third quarter of 2026, the company decided to hold a performance presentation of Luoyang Molybdenum Industry in the third quarter of 2026. In today's event, the main members of the management of Luoyang Molybdenum Industry visited the Shanghai Roadshow Center and will communicate with investors. Everyone is welcome to participate actively.
Questions and answers
Investor
Hello, General Manager Xu! Concerned that the company has completed the acquisition of gold mines in Ecuador and Brazil in the past two years. Will the future expansion of copper and gold resources still consider new overseas mining mergers and acquisitions, or will it focus on the development and operation of acquired mines at this stage?
XU HUIBoard Secretary, CMOC GROUP
Dear investors, hello. The company firmly implements the "copper and gold bipolar" strategy, attaches importance to building resource advantages through strategic mergers and acquisitions, adheres to the "multi-variety, multi-country, multi-stage" M & a strategy, and also pays attention to continuously promoting planning, construction and daily operation capabilities, releasing the resource potential of acquired assets. Continue to inject momentum into the company's long-term development. Thank you for your interest!
Investor
At present, the basic supply of copper is tight, but why is the price of copper falling? Will the price of copper rise in 2027?
XU HUIBoard Secretary, CMOC GROUP
Dear investors, at present, the US copper tariff policy is basically on hold. The recent fluctuation of copper price is greatly affected by macro factors, and the sales price of the company's copper products follows the market. Thank you for your interest.
Investor
Is the production progress of KFM Phase II in 2027 in line with expectations? Gold business 2028 20 tons of production capacity target to achieve the path?
XU HUIBoard Secretary, CMOC GROUP
Dear investors, the company's KFM Phase II project is progressing smoothly and is expected to be put into operation in 2027. At present, the company has two major gold projects in Brazil and Ecuador. Gold production guidance for 2026 is 6-8 tons, all from Brazilian gold projects. The gold mine in Ecuador is a greenfield project, and the company plans to put it into production in 2029. Specific capacity planning is subject to the company's announcement. Thank you for your interest.
Investor
Four gold mines in Brazil contributed 4.707 billion yuan in revenue in the first three quarters, with gross profit margin of 37.92%. May I ask Secretary Dong: * At present, has the delivery and consolidation of gold mines in Brazil been completed smoothly? In terms of cross-cultural management, local community relations and environmental compliance, what specific measures have been taken to ensure that "resource advantages are transformed into operational advantages"? * Combined with the current high gold price, is there any further update on the company's annual production guidance and profit contribution expectations for the gold sector?
XU HUIBoard Secretary, CMOC GROUP
Dear investors, the delivery and consolidation of the company's gold mines in Brazil have been smoothly implemented. The company has been operating in Brazil for more than ten years, and has a deep understanding of local culture, community, compliance and other aspects. Through the management mode of China-Brazil integration, it has effectively improved the operational efficiency of mining, dressing and smelting. At the beginning of the year, the company has disclosed the production guidance of various mineral products, and the annual production guidance of gold is 6-8 tons.
Thank you for your interest.
Investor
By the end of the third quarter, the company's construction in progress totaled 10.493 billion yuan, an increase of 158.85% over the end of last year, and a large outflow of cash flow from investment activities.
May I ask Secretary Dong: * Under the current high-intensity capital expenditure cycle, will the company's future dividend policy be affected? * Combined with the company's current extremely low valuation level (the current stock price corresponds to PE in 2026 is only about 9.9 times), does the company have a long-term plan to boost market confidence and give back to minority shareholders through share repurchase and increasing dividend ratio?
XU HUIBoard Secretary, CMOC GROUP
Dear investors, thank you for your attention. The expansion of the company's construction in progress compared with the end of last year was mainly due to the increase in investment in project construction. The cash outflow from investing activities was mainly due to the increase in payment for the acquisition of gold mine projects. The company attaches great importance to the return of investors, and will balance and pay equal attention to the continuous business development and cash return of shareholders in the use of funds.
If there are relevant matters, the company will disclose them according to the regulations. Please pay attention to the company's announcement.
Investor
According to the results, cobalt production in the first three quarters increased by 13.32% year-on-year, but sales dropped by 75.19% year-on-year. The announcement explained that this was affected by the cobalt export quota policy of the Democratic Republic of the Congo (DRC) government. May I ask Secretary Dong: * What is the current inventory backlog of the Company's cobalt products? Is there a greater risk of storage costs and depreciation? : Is there a clear timetable for lifting or adjusting the export quota policy of the Democratic Republic of the Congo?
What level of communication is the company's management doing with the local government to alleviate this restriction? * In the context of the recent sustained decline in cobalt prices, does the company have a hedging mechanism or an industrial chain extension plan to stabilize the risk of price fluctuations?
XU HUIBoard Secretary, CMOC GROUP
Dear investors, please refer to the semi-annual report of the Company for 2026 for the inventory of the Company's cobalt products. The finished product of the company's cobalt is cobalt hydroxide, which has stable chemical properties, simple storage conditions and low storage costs. The cost of self-produced mine products of the Company is competitive in the industry. Inventories are measured at production cost, and it is expected that there will be no impairment. At present, the export quota of Congo (DRC) is clear until 2027, and it is not clear whether the policy will change in the future.
The company will maintain active communication with the local government. Thank you for your interest.
Investor
Copper production reached a record high in the third quarter (208,700 tons), but the market was concerned that copper production costs increased significantly in the third quarter (mainly affected by the rising price of sulfuric acid).
May I ask Secretary Dong: * In view of the rising cost of sulfuric acid and other auxiliary materials, does the company have corresponding cost reduction and efficiency enhancement measures (such as the waste heat steam power generation project of KFM acid plant) to stabilize the cost pressure? * Looking forward to 2027 and beyond, with the successive production of KFM Phase II and TFM Phase III, is the company confident to achieve the long-term strategic goal of 1 million tons of copper production after 2028 as scheduled?
XU HUIBoard Secretary, CMOC GROUP
Dear investor, hello. The company’s KFM acid plant is under construction and is expected to be put into operation next year, effectively reducing the amount of acid purchased externally. The company’s 2026 production guidance is 760,000 to 820,000 tonnes, which has already reached the lower end of the 2028 production target. KFM Phase II will bring an annual average increase of 100,000 tonnes in copper production. Please refer to the company’s announcements for the production plan for TFM Phase III.
The company has excellent copper resource endowment and can fully support achieving the company’s production target of 1 million tonnes. Thank you for your attention.
Investor
Has the implementation rules of the new tax system for 55% of mining by-products in the Democratic Republic of Congo (DRC) been implemented? How to quantify the impact on the company's copper cost per ton? In addition, after the safety incident in the mining area in early October, is the production and operation of TFM/KFM normal?
XU HUIBoard Secretary, CMOC GROUP
Dear investors, hello. The company's copper products are mainly cathode copper. The matters you mentioned do not involve the company's products and have no impact on the company. The production and operation of the company's mines in the Democratic Republic of the Congo are all normal. Thank you for your interest!
Investor
I would like to ask the management: What is the progress of copper production in the first three quarters, and whether the fourth quarter can exceed the guidance of 800,000 tons set at the beginning of the year? In addition, in view of the company's strategic goal of moving towards the top three "million-ton copper enterprises" in the world, what are the specific construction nodes, investment scale and expected production schedule of KFM Phase II and TFM Phase III in Congo (DRC)?
XU HUIBoard Secretary, CMOC GROUP
Dear investor, hello. The company’s 2026 copper production guidance is 760,000 to 820,000 tonnes, and it has completed approximately 76% of the midpoint of the full-year production guidance. Construction of the company’s KFM Phase II is progressing smoothly and on schedule, with production planned to begin in 2027. Once Phase II reaches full capacity, it can bring an annual average of 100,000 tonnes of copper production. Please refer to the company’s announcements for specific project progress and plans.
Investor
I would like to ask the management: In 2026, the company will promote the "copper and gold bipolar" strategy. After the consolidation of four gold mines in Brazil, what is the actual production and net profit contribution in the first three quarters? What is the full sustaining cost (AISC) of a single gram of gold? What is the progress of the follow-up mining plan for the Odin Gold Mine in Ecuador?
XU HUIBoard Secretary, CMOC GROUP
Dear investors, please refer to the company's third quarter report for gold production and gross profit data. The Odin Gold Mine in Ecuador is currently in the planning stage and is scheduled to start production in 2029. Thank you for your interest.
ModeratorSSE Roadshow Center
The performance presentation of Luoyang Molybdenum Industry in the third quarter of 2026 was successfully concluded. Thank you for the active participation of investors and netizens. If you have further questions, you can keep communicating with the company through the e interactive platform of Shanghai Stock Exchange. Thank you!
About this transcript
The call was held in another language and translated. The summary, guidance, analyst focus, and tone are automated and should be checked against the call before being relied on. Names and figures can be misheard. Listen to the replay.