    AI data-center construction, lease commencement, and campus cost overruns now drive execution risk.

    Filed Jul 29, 2026
  • FY2025 10-K risk factors
    85 risks

    The company relies heavily on a single customer for 93 percent of revenue in fiscal year 2025 and is concentrated in North Dakota data centers. Massive capital needs, debt agreements like the SMBC Credit Agreement, and the construction of Polaris Forge 1 dominate risk exposure. Operations depend entirely on continuous high-voltage power availability and vulnerability to third-party outages.