Summary
Management framed the quarter around regulated utility execution and infrastructure growth, while emphasizing that Bakken East remains subject to board approval and project economics.
- Bakken East agreements now cover nearly all binding open-season interest, but the FERC filing moved from the third quarter to the fourth quarter.
- Data-center economics remain excluded from growth guidance pending regulatory approval, with management describing a capital-light model that shares benefits with retail customers.
- The company reaffirmed its 2026 outlook and said Bakken East would remain incremental to the current capital program.
Guidance
- 93 cents to a dollar 2026 earnings per share guidance
- 8%6 to 8 percent long-term earnings per share growth objective
- 3.1BApproximately 3.1 billion 2026-2030 capital program
- 1.1B1.1 billion 2026-2030 electric business investments
- 1.4B1.4 billion 2026-2030 natural gas distribution investments
- 643M643 million 2026-2030 pipeline investments
What analysts pressed on
- 01Bakken East financing: management said it was evaluating all options and expressed confidence in financing, but gave no specific structure.
- 02Bakken East timing: the FERC 7C filing is now expected in the fourth quarter, with FID ahead of filing but no specific date provided.
- 03Bakken East capacity: management is designing for 1.4 BCF per day and said future expansion could require additional compression and capital.
- 04Polaris Forge 3 economics: incremental margin benefits the company and retail customers, but will not enter guidance until regulatory approval.
- 05Data-center community concerns: management said it is engaging locally and feels good about conversations in communities with signed agreements.
Notable disclosures
- 1.2BNearly 1.2 billion cubic feet per day of Bakken East capacity is covered by agreements, with an option that could bring volumes close to original binding interest.
- Over 1 gigawatt of data-center load is under signed electric service agreements, with approximately 240 megawatts online.
- 430 megawatts is the potential full-capacity load for the Polaris Forge 3 campus, pending North Dakota commission approval.
- Bakken East's FERC filing shifted to the fourth quarter after precedent-agreement negotiations took longer than expected.
Risks raised
- Bakken East's final investment decision remains pending, and financing, commercial options and project design are still being evaluated.
- Bakken East's planned 1.4 BCF-per-day design exceeds currently contracted volumes, leaving additional capacity dependent on customer demand.
- The Polaris Forge 3 agreement and related regulatory filings remain subject to North Dakota commission approval.
- Data-center projects face community concerns that management said require continued engagement and explanation of customer benefits.
Tone: Positive 0.65
Management emphasized improved utility results, signed pipeline agreements and data-center growth, while acknowledging delayed filing timing and unresolved approvals.
Who spoke
Company
- Brent MillerTreasurer
- Nicole KivistoPresident and Chief Executive Officer
- Jason VollmerChief Financial Officer
- Unidentified Management
Analysts
- Andrew KadavyAnalyst, Wells Fargo
- Unidentified AnalystAnalyst
- Ryan LevineAnalyst, Citi
Full transcript
Analyst questions are marked with a bar. Timestamps are into the recording.
Prepared remarks
Ladies and gentlemen, thank you for joining us and welcome to the MDU Resources Group in Q2-2026 earnings conference call. After today's prepared remarks, we will host a question and answer session. If you would like to ask a question, please raise your hand. If you've dialed in to today's call, please press star 1 to raise your hand. I will now hand the conference over to Brent Miller, Treasurer of MDU Resources Group. Brent, please go ahead.
Brent MillerTreasurer
Thank you and welcome everyone to the MDU Resources Group Q2-2026 earnings conference call. Our earnings release and supporting materials for this call are available on our website at MDU. com under the Investors section. Leading today's call are Nicole Cavisto, President and Chief Executive Officer and Jason Volmer, Chief Financial Officer of MDU Resources Group. During today's call, we will make certain forward-looking statements within the meaning of the Federal Securities Laws. Please refer to our SEC filings for a discussion of risks and uncertainties that could cause actual results to differ. I will now turn the call over to Nicole for her prepared remarks. Nicole?
Nicole KivistoPresident and Chief Executive Officer
Thank you, Brent, and good afternoon everyone. We appreciate you joining us today and for your continued interest in MDU resources. This morning, we reported second quarter 2026 earnings of $21.3 million or 10 cents per share. Our results reflected continued execution across our regulated utility and pipeline businesses. New rates, customer growth, investments such as Badger Wind Farm and higher retail sales volumes helped drive the results. We delivered solid results while also continuing to advance strategic infrastructure opportunities that continued to support long-term growth. A key highlight for the quarter was certainly the continued advancement of the proposed Bakken East pipeline project. With recently signed precedent agreements, we now have executed agreements with all customers that submitted binding open season interest, totaling nearly 1.2 billion cubic feet per day of transportation capacity with a negotiated option in place that may increase contracted volumes to nearly all of the original interest from our binding open season.
We continue to design the project for 1.4 billion cubic feet per day of transportation capacity. Overall project design is being finalized based on confirmed customer volumes and delivery locations before a final investment decision is made, which is expected ahead of a FERC 7C filing. This application is now anticipated to be filed in the fourth quarter of 2026. The proposed in-service states of phase one in late 2029 and phase two in late 2030 remain unchanged. As development progresses, we continue to evaluate financing, partnership and other commercial options to support the projected 2.7 billion to 3.2 billion dollar project. The potential Bakken East investment remains incremental to our current capital program. We also continue to see encouraging development activity across our service territory, including data center opportunities and broader infrastructure demand.
Our approach to serving data centers is grounded in protecting existing customers and ensuring that growth creates value for the communities we serve. Data center customers are responsible for paying the costs associated with connecting to and being served by the electric system, including infrastructure and energy related expenses. At the same time, the additional revenue generated from serving these customers can help support the electric system and contribute to reducing certain fixed costs for existing retail customers by allocating them across a broader customer base. This current approach creates benefits for all customers. During the quarter, we did enter into an electric service agreement with Applied Digital to serve Polaris Forge 3 and A. I. Factory near center, North Dakota.
At full capacity, the campus would require 430 megawatts of electricity. Approval of the ESA and other regulatory filings by the North Dakota Public Service Commission is pending. We now have over 1 gigawatt of data center load under signed ESA's with approximately 240 megawatts currently online with additional volumes expected over the next few years as additional buildings are constructed. On the electric regulatory front, we did file a North Dakota general rate case on June 30th, 2026 requesting an annual revenue increase of approximately 34.5 million with interim rates of approximately 26.3 million requested to begin on September 1st of this year. The filing reflects electric infrastructure investments, normal depreciation, reliability improvements, system safety and higher operation and maintenance expense.
In Montana, interim rates reflecting an annual increase of approximately 10.4 million remain in effect, subject to refund and a settlement agreement of 10 million has been filed in his pending commission approval. In Wyoming, our general rate case settlement was approved for an annual increase of 5.8 million with rates effective April 1st, 2026. Also in June, the North Dakota Public Service Commission approved a route permit for the Jamestown to Elendale Transmission Project. This project is expected to enhance reliability, improve resiliency, reduce transmission congestion and support access to lower cost energy across the region.
At our natural gas distribution segment, positive regulatory outcomes in Idaho, Washington, Montana and Wyoming, as well as higher retail sales volumes and continued customer growth supported improved year over year results. In Washington, we did file a multi-year natural gas case requesting an annual revenue increase of 25.1 million in year one and 18.1 million in year two. Our Oregon general rate case remains pending with a multi-party settlement agreement, which was filed on July 31st, 2026, with a requested annual increase of approximately 12.2 million. We also do anticipate filing a Minnesota general rate case later this year. At our pipeline segment, strategic growth initiatives continue to advance. The line section 32 expansion project remains on schedule following our FERC section 7C application filing in March of 2026 and continues to target at late 2028 in-service state subject to regulatory approvals.
Development activities for the potential-minded industrial project also continue under agreements currently extended through late 2026. In addition, our pipeline business filed a FERC rate case on May 29th of this year requesting a $31 million annual revenue increase. Approximately 30 percent of the requested revenue increase is due to proposed new depreciation and amortization rates. FERC accepted and suspended the proposed rates on June 30th with rates to become effective December 1st, 2026, subject to refund and the outcome of hearing procedures if a settlement with our customers and FERC is not reached.
Looking ahead, we are reaffirming our 2026 earnings per share guidance range of 93 cents to a dollar. This guidance is based on assumptions including normal weather, economic and operating conditions for the remainder of the year, continued customer growth, successful execution of approved capital investment programs and constructive regulatory outcomes. Our long-term earnings per share growth objective remains at 6 to 8 percent. Our capital program for 2026 through 2030 totals approximately 3.1 billion with planned investments of approximately 1.1 billion in our electric business, 1.4 billion at our natural gas distribution business and 643 million at our pipeline.
We remain focused on discipline execution of this plan while advancing additional infrastructure opportunities that support customers, communities and stockholders. As always, MD resources is committed to operating with integrity and with a focus on safety. We remain dedicated to delivering safe, reliable, cost effective and environmentally responsible energy services while positioning the company for compelling long-term growth. And with that, I will now turn the call over to Jason for the financial update. Jason?
Jason VollmerChief Financial Officer
Thank you, Nicole. As Nicole mentioned, we announced this morning second-quarter earnings of 21.3 million or 10 cents per share compared to 13.7 million or seven cents per share for the second quarter of 2025. On a year-to-date basis, earnings were 102.1 million or 49 cents per share compared to 95.7 million or 47 cents per share for the first six months of last year. Trained to our individual businesses, our electric utility reported second-quarter earnings of 14.7 million compared to 10.4 million for the same period in 2025.
Results benefited from higher retail sales revenue, including recovery mechanisms associated with renewable investments such as the Badger Wind Farm, which contributed 3.3 million earnings during the quarter. Interim rates in Montana and new rates in Wyoming along with higher retail sales volumes across all major customer classes also contributed to the increase.
Our natural gas distribution segment reported a seasonal second-quarter loss of 3.9 million compared to a seasonal loss of 7.4 million in the second quarter of 2025.
The improved year-over-year result was primarily driven by new rates in Idaho, Washington, Montana, and Wyoming, as well as higher retail sales volumes across all customer classes. Retail sales volumes increased 6.7% and customer growth was 1.6% year-over-year. These benefits were partially offset by higher interest expense, resulting from higher long-term debt balances. The pipeline segment earned 14.4 million in the second quarter compared to 15.4 million in the same period in 2025. The decrease was driven by lower income and higher depreciation and amortization expense from a growth project place in service. These impacts were partially offset by continued customer demand for short-term natural gas transportation contracts and interruptible storage services, along with contributions from previously constructed growth projects, including a contracted volume increase.
The other category reported a second quarter net loss of 3.9 million compared to a net loss of 4.7 million in the same period last year. The year-over-year improvement was primarily due to discontinued operations and associated with a $1.5 million tax benefit-related strategic initiative costs.
We continue to maintain a strong balance sheet and ample access to working capital to finance operations through our peak periods. That summarizes our financial highlights for the we appreciate your interest in your resources and ask now that we open the line for questions. Operator.
Questions and answers
Thank you. We will now begin the question and answer session. If you would like to ask a question, please raise your hand now. If you have dialed into today's call, please press star 1 to raise your hand. Please stand by while we compile the Q&A roster. Your first question comes from the line of Konstantin Letnev with Wells Fargo. Your line is open. Please go ahead.
Andrew KadavyAnalyst, Wells Fargo
Hi. Actually, it's Andrew Kadavion from Konstantin right now. Maybe on the financing options for Bakken East, we've seen some peers use a variety of instruments to finance these bigger projects. We've seen any favorable markets out there that could help you efficiently finance the project.
Jason VollmerChief Financial Officer
Certainly this is Jason. I can feel that one. I think, again, as we have stated before, at this point, we're very excited to have reached executing all of the press and agreements we have in place as we've been working towards that progress. We continue to look at all options as we think about financing project of this size and scope. As you mentioned, we've seen others out there too. We've been very focused on getting these press agreements signed and getting to the point of a decision. Of course, you need to get in front of our board to look at a final investment decision on this project. I can say to say, we'll look at all options out there, but feel very confident in the ability to finance a project like this, and certainly some good appetite out there for these types of assets today.
Would that be part of the board's FID decision, and is that selling schedule for a third quarter, or is that where we're looking at fourth quarter for that now? Yeah. Right now, we've stated a little bit of a new update in our release this quarter. We are looking to make our 7C filing in the fourth quarter. I think we would have previously looked at third quarter based on the schedule. Certainly, some of the press agreement negotiations took a little bit longer, as Nicole mentioned, these have been some of these recently signed here. So we will continue to bring our board up to speed on where we're at with the project. They've been certainly involved all the way along.
Work is continuing on this project and has continued from the beginning since we started looking at this. So I'm not going to be specific on a timeline date yet. I think we need to go through the process of now getting the right information in front of our board and make a decision in the right manner, but certainly what happened ahead of the 7C filing, which we are now expecting to happen in the fourth quarter.
Appreciate it. Thank you. I'll leave it there.
Your next question comes from the line of Julian DeLamoula Smith with Jeffries. Your line is open. Please go ahead.
Unidentified AnalystAnalyst
Hi, team. It's actually Tanner on for Julian. Good afternoon.
Nicole KivistoPresident and Chief Executive Officer
Good afternoon, Tanner. Thank you. And thanks for the new Bocanese disclosures here. Could you maybe provide a little more information on the negotiated option in place? The strategic rationality behind it and how you would classify the commercial alternatives in not taking the option? Thanks. Yeah, I can take that. So to appreciate the question, and I guess I just want to start by echoing what Jason said. I really want to give a shout out to the WBI team. Extremely proud of the milestone here that we announced today with the recently signed precedent agreements that get us to all customers really that were in the non-binding open season showed up here. So that's real positive news. We did reference the option, as you mentioned, and essentially what we've done with that customer is they're working, all customers are working on timing with their applicable customers.
And so we worked an arrangement out where they have an option to essentially add more volumes at an already negotiated agreement. And so essentially, if that happens, what we alluded to in the release is that gets us very close to that open season amount. Now, saying that, I will say a key data point that we disclosed here also would be that we still are designing the project at 1.4 BCF a day. So feel good about that.
And then just highlighting a couple of the other key updates which Jason alluded to too, which is with the precedent agreements being recently signed, we did allude to moving that 7C filing back to the fourth quarter. And note that we would make a final investment decision ahead of that. In service dates, as we mentioned, they'll remain unchanged. Understood, great. Thanks. Is the state backstop a portion of the executed agreements or have they or have you found an off taker to stand in their place? Yes, the state is part of the precedent agreements that we have signed.
Understood, thanks. And then maybe just following up on the Polaris Forge 3 ESA, you're in front of the commission requesting approval. Can you speak to the magnitude of margin uplifts here relative to what we're seeing at the Ellendale campus and maybe zooming out since you've also recently just filed your electric rate case in the state? Does this give you confidence to be able to elongate the period between filings given the support to earned ROEs from the capital light ESA? Thanks. Yeah, absolutely. We certainly are excited about the ESA that we signed. As we disclosed, it's 430 megawatts. As you mentioned, rightfully so. We do have this in front of the state of North Dakota for approval.
And so, as you can imagine, we would be waiting to get the appropriate approvals before we'd contemplate including that in any of our numbers or providing any financial guidance. So, right now, that would not be contemplated in what we're talking about from a long-term growth rate perspective. Certainly, the way we are working through these negotiations with data center customers. You've heard us talk about this in the past. We are working under a capital light model as of today. And so, incremental margin on data center load is a benefit to the company. But I would say it's also a benefit to our customers. So, we really do feel like it's a win-win. So, yes, there is a benefit to the company.
But as we've talked about with investors in the past, we are sharing a piece of that margin with our retail customers. So, they are getting a credit on their bill as well. And then, in addition to that, the data center takes on more of that transmission expense that otherwise would have been allocated to our retail customers. So, we're also seeing bill impacts, bill reductions to retail customers because of that. So, that kind of gives you, here's the company side of it and here's the customer side of it. But the bottom line is, the center ESA right now, we are still waiting for approval and final move forward on that with the state before we would incorporate something like that in our guidance.
Great. I'll leave it there. Thank you.
Your next question comes from the line of Aiden Kelley with JP Morgan. Your line is open. Please go ahead.
Unidentified AnalystAnalyst
Hey, guys. Thanks for the time today.
Nicole KivistoPresident and Chief Executive Officer
Absolutely. Thank you for joining. Yeah, of course. So, just want to hone in on Bock and East again, clearly strong commercial momentum to date with the 1.2 BCF security mentioned. And you're still kind of designing for 1.4 BCF. I guess my question is, are there any factors that would cause you to expand the Bock and East pipe? I know in the past, you've kind of spoken to an overbuilt scenario and as a consideration, so just curious if you could comment on the potential there in your thoughts in general. Yeah. So, as we mentioned in the news release and, you know, I also reiterated as part of my talking points here today, we are still currently working through that overall design.
So, with these recently signed precedent agreements, you know, we will look at what makes sense in terms of designing the project so that we can have expandability, but also designing the project so that it meets the financial hurdles we need from a board as well as a shareholder perspective. So, it's a balancing act, but certainly we will be looking at that and contemplating that as we move to a final investment decision. Great. Understood makes sense. And I guess just teeing it all up, you kind of laid out, you know, potential, you know, FID coming before the 7C filing in 4Q and you kind of need to go to the board for some considerations there. I guess just like for the investing community, when should we kind of expect you to refresh the capital plan and kind of roll in this block and East estimate, is that like kind of, you know, on the tails of 4Q or just any kind of color on the timing there as you kind of see it today?
Jason VollmerChief Financial Officer
Okay, and I can take that one. So, our normal process for updating capital would really be kind of that late November timeframe. So, typically, after our third quarter board meeting meeting with our board updating along the way. Now, that said, you know, something the size of a box and East project here would be incrementally large increase to that. So, I think when we get to a board, we've got an FID decision, a little more, you know, clarity around exactly what impacts this could have, should we decide to proceed here, then I think we would update the market at that point with some sort of a maybe revised range. As you know, right now, we've put a range out there in the neighborhood of 2.7 to 3.2 BC, or 3 billion of the capital range, sorry, on that one.
So, that is something that we will continue to refine as we go along as we get closer to the the ultimate decision here. But I think, you know, we'll probably narrow that in. And certainly, by the time we get to our November normal capital increase cycle, we would have a kind of a working assumption built into our capital plan again, if our board decides to, you know, move forward with this project. And certainly, again, at this point, we're excited about the progress we've made to date. Great. Thanks. I'm sorry, just one follow-up question on my first question, actually, is it so it is possible upsized? And then like, I guess, when would that decision be made if so?
Yeah, and I can maybe just comment on that. So, again, we're designing for 1.4 BC after it's really going to support the demand that we are getting here throughout the contracting process where we've got to at this point in time. To Nicole's point, there would be the ability for us to expand on that in the future. Should we see additional demand arise in the future? That would probably take some additional capital, maybe in the form of additional compression, things like that. So, those are things we'll make decisions on as we go but right now, we are designing to the demand that we have today. But we would have the ability to potentially upsize this in the future if, you know, more demand showed up in the future periods.
Great. Appreciate all the time today. Always up there. Thanks. Thank you. Thank you. A reminder, if you would like to ask a question, please press star 1 to raise your hand.
Your next question comes from the line of Chris Ellinghouse with Seaport William Shank. Your line is open. Please go ahead.
Unidentified AnalystAnalyst
Hey, everybody. How are you today?
Unidentified Management
Doing good, Chris. You just give a little color. Chris, are you still there? We can't hear you right now.
A gentle reminder to unmute locally.
Your next question comes from the line of Ryan Levine with City. Your line is open. Please go ahead.
Ryan LevineAnalyst, Citi
Hi, everybody. I'm going to start off on the North Dakota Data Center front. Given that we're seeing broad calls and things publicly around increasing community engagement from on some of the concerns around data centers in the state, how's MDU approaching the engagement on those potential issues and trying to advance projects that may support close growth in the region?
Nicole KivistoPresident and Chief Executive Officer
Yeah, so as it relates to where we are currently serving, I'm assuming you're talking about the data center load and conversations around that balancing act. I just want to make sure I'm answering your question.
Ryan LevineAnalyst, Citi
Correct. Yes.
Nicole KivistoPresident and Chief Executive Officer
So I think as we think about where we're at today in the communities that we've got signed ESA's, we feel pretty good about how that community conversation is moving forward. That being said, we do believe that we need to continue to tell our story in terms of how we are serving data centers and what the potential benefit is not only to our existing retail customers, but to the communities at large. So we have been engaged with the communities. We've been engaged in other discussions locally in terms of getting that message out, highlighting that information on our website, visiting with our employees about it, etc. Just to make sure that it's understood in terms of how we are serving data center loads.
But specifically as it relates to those conversations in the areas where we have signed ESA's, we feel good about where we're at today.
Ryan LevineAnalyst, Citi
Thanks. And then just to clarify, given all the momentum around the pipeline expansion and you indicating that no FID until the fourth quarter, just to confirm there's no meaningful milestones that need to be achieved between now and then to move forward with the project or any clarification you're able to make to around that particular issue.
Nicole KivistoPresident and Chief Executive Officer
Yeah, I guess I would just clarify your question with the response that is making sure you understand. What we said is we would intend to have an FID before the seven C filing and the seven C filing is scheduled for the fourth quarter. So just want to clarify, we didn't technically say for sure that's when we would move forward with an FID would be the fourth. We said it would be before the filing of that seven C. So just want to clarify that in terms of other major milestones.
As you can imagine, we have continued work on this project all the way through this as we were negotiating press and agreements. We have been doing numerous things, whether it's boots on the ground activity, whether it's continuing to think about how we might finance a project of this size. So throughout that whole process, we have certainly been engaged with our board in this discussion as well. And so we'll continue to do that as we head into a final investment decision.
Appreciate the disclosure. Thank you. Thank you.
There are no further questions at this time. I will now turn the call back to Nicole Cavisto for closing remarks.
Nicole KivistoPresident and Chief Executive Officer
All right. I want to thank everyone again for joining us today and for your thoughtful questions. We certainly appreciate your continued interest in and support of MDU resources. As we move through the remainder of 2026, we remain focused on discipline, execution of our capital program, constructive regulatory engagement in advancing infrastructure opportunities that support safe, reliable and affordable energy for our customers.
Finally, I want to close by thanking all of our employees for their ongoing commitment to safety, reliability, operational excellence, and customer service. And with that, we look forward to staying engaged with all of you throughout the year. Operator, you may conclude the call.
This concludes today's call. Thank you for attending. You may now disconnect.
Other MDU Resources Group earnings calls
- Q3 2026 earnings call
Management framed the quarter around advancing Bakken East while reaffirming its 2026 outlook and stressing disciplined, customer-protective growth investment.
Nov 05, 2026Positive0.45
About this transcript
The summary, guidance, analyst focus, and tone are automated and should be checked against the call before being relied on. Names and figures can be misheard. Listen to the replay.