What the changes say
- Montauk Renewables faces new credit facility covenants tied to D3 RIN prices and local permitting opposition risks for renewable projects.
What changed since the prior 10-K
New
- NewRegulatory Risks
solely on the condition that we carry out certain corrective measures to the proposed project. Opposition to our projects’ requests for permits or successful challenges or appeals to permits issued for our projects could adversely affect our operating plans
Local population opposition or permit challenges could delay construction targets, increase requirements, or prevent obtaining necessary building permits for renewable energy plants.
- NewCybersecurity and Information Technology Risks
minimum Consolidated EBITDA (as defined in the Credit Agreement) of at least $10.0 million
Our Credit Agreement requires a minimum Consolidated EBITDA of $10.0 million and defaults if average monthly D3 RIN prices fall below $1.00 per RIN.
Dropped
- DroppedBusiness Strategy Risks
Any future acquisitions, investments or other strategic relationships that we make could disrupt our business, cause dilution to our stockholders or harm our business, financial condition or operating results
- DroppedBusiness Strategy Risks
We are subject to volatility in prices of RINs and other Environmental Attributes
- DroppedBusiness Strategy Risks
The failure of our hedge counterparties or significant customers to meet their obligations to us may adversely affect our financial results
- DroppedRegulatory Risks
that encourage the use of other energy sources over renewable energy, could adversely affect our business, financial condition and results of operations
- DroppedRegulatory Risks
the amount of energy that our projects are able to deliver. Any of these events, to the extent not fully covered by insurance, could adversely affect our business, financial condition and results of operations
- DroppedRegulatory Risks
Our business is subject to risks arising out of climate change, which could result in increased operating costs
- DroppedCybersecurity and Information Technology Risks
a total leverage ratio of not more than 3.00 to 1.00
- DroppedCybersecurity and Information Technology Risks
in Item 7 “Management’s Discussion and Analysis of Financial Condition and Results of Operations—Liquidity and Capital Resources.”
- DroppedCommon Stock Risks
Our issuance of additional capital stock in connection with financings, acquisitions, investments, our equity incentive plans or otherwise will dilute stockholders
- DroppedCommon Stock Risks
Our ability to pay regular dividends on our common stock is subject to the discretion of our Board of Directors
Reworded
- 78% rewrittenRegulatory Risks
Revenue from any projects we complete may be adversely affected if there is a decline in public acceptance or support of renewable energy, or regulatory agencies, local communities, or other third parties delay, prevent, or increase the cost of constructing and operating our projects
Updated to include regulatory agencies and local communities delaying or increasing costs of constructing and operating renewable projects.
- 76% rewrittenRegulatory Risks
Negative attitudes toward renewable energy projects from the U.S. government, other lawmakers and regulators, and activists could adversely affect our business, financial condition and results of operations
Removed mention of lack of legislative focus on programs and regulations from the description of negative attitudes toward renewable energy.
- 68% rewrittenCybersecurity and Information Technology Risks
Our senior credit facility may not be sufficient to meet our financial needs and contains financial and operating restrictions that may limit our business activities and our access to other forms of credit
Updated with March 9, 2026 senior credit facility terms consisting of up to $200.0 million in senior indebtedness maturing in March 2031.
- 67% rewrittenCommon Stock Risks
Future sales of our common stock in the public market could cause the market price of our common stock to decline
Removed specific reference to MNK promissory note pledged shares and associated loan obligation sales impacting common stock price.
- 65% rewrittenCybersecurity and Information Technology Risks
We are in our last year of being an emerging growth company and will soon be required to comply with certain requirements that apply to other public companies
Added disclosure that starting with the 2026 Form 10-K, the company will no longer qualify as an emerging growth company.
Was: For as long as we are an emerging growth company, we will not be required to comply with certain requirements that apply to other public companies
- 65% rewrittenBusiness Strategy Risks
The profitability of our renewable fuel projects may be limited by our ability to dispense fuel to separate RINs and the volatility of the price of RINs
Added specific mechanics regarding dispensing RNG through permitted channels to separate RINs and associated supply-demand pricing effects.
Was: Our renewable fuel projects may be exposed to the volatility of the price of RINs
- 60% rewrittenBusiness Strategy Risks
We plan to expand our business in part through developing RNG recovery projects at landfills and livestock farms, including our Turkey, North Carolina location, but we may not be successful
Updated EPA candidate landfill figures from 463 total and 38 sufficient sites to 444 total and 32 sufficient sites.
Was: We plan to expand our business in part through developing RNG recovery projects at landfills and livestock farms, but we may not be able to identify suitable locations or complete development of new projects
- 57% rewrittenRegulatory Risks
The reduction or elimination of governmental economic incentives for renewable energy projects or other related policies could adversely affect our business, financial condition and results of operation
Retained prior year text regarding government economic incentives and RFS program details.
- 56% rewrittenOperational Risks
We have significant customer concentration, with a limited number of customers accounting for a substantial portion of our revenues
- 55% rewrittenOperational Risks
The concentration in revenues from five of our projects and geographic concentration of our projects expose us to greater risks of production interruptions from severe weather or other interruptions of production or transmission
- 55% rewrittenOperational Risks
Our success depends, in part, on technological innovation to stay ahead of market competitors
- 55% rewrittenCybersecurity and Information Technology Risks
If we identify material weaknesses in the future or otherwise fail to maintain an effective system of internal controls, we may be unable to accurately or timely report our financial condition or results of operations, which may adversely affect our business
- 46% rewrittenBusiness Strategy Risks
Our dairy farm project has, and any future digester project will have, different economic models and risk profiles than our landfill facilities, and we may not be able to achieve the operating results we expect from these projects
- 35% rewrittenBusiness Strategy Risks
While we currently focus on converting methane into renewable energy, in the future we may decide to expand our strategy to include other types of projects. Any future energy projects may present unforeseen challenges and result in a competitive disadvantage relative to our more established competitors
- 35% rewrittenRegulatory Risks
Our business is subject to the risk of extreme or changing weather patterns
- 32% rewrittenCybersecurity and Information Technology Risks
Our business could be negatively affected by security threats, including cybersecurity threats and other disruptions
- 31% rewrittenCybersecurity and Information Technology Risks
We may be required to write-off or impair capitalized costs or intangible assets in the future or we may incur restructuring costs or other charges, each of which would harm our earnings
- 30% rewrittenRegulatory Risks
Existing regulations and policies, and future changes to these regulations and policies, may present technical, regulatory and economic barriers to the generation, purchase and use of renewable energy, and may adversely affect the market for credits associated with the production of renewable energy
- 29% rewrittenOperational Risks
Our use and enjoyment of real property rights for our projects may be adversely affected by the rights of lienholders and leaseholders that are superior to those of the grantors of those real property rights to our projects
- 28% rewrittenBusiness Strategy Risks
difficulties in identifying, obtaining and permitting suitable sites for new projects
- 27% rewrittenCybersecurity and Information Technology Risks
We are dependent upon our relationships with Waste Management and Republic Services for the operation and maintenance of landfills on which several of our RNG and Renewable Electricity projects operate
- 26% rewrittenBusiness Strategy Risks
Our commercial success depends on our ability to identify, acquire, develop and operate individual renewable energy projects, as well as our ability to maintain and expand production at our current projects
- 24% rewrittenRegulatory Risks
We may be unable to obtain, modify or maintain the regulatory permits, approvals and consents required to construct and operate our projects
- 23% rewrittenOperational Risks
Our renewable energy projects may not generate expected levels of output
- 22% rewrittenOperational Risks
Our projects are exposed to the risks inherent in the construction and operation of renewable energy projects, such as breakdowns, manufacturing defects, extreme weather, natural disasters, terrorist attacks and sabotage. We are also exposed to environmental risks
All 46 risk factors
Headings as the filing states them, in filing order.
Operational Risks
- 01Our renewable energy projects may not generate expected levels of output23% rewritten
- 02The concentration in revenues from five of our projects and geographic concentration of our projects expose us to greater risks of production interruptions from severe weather or other interruptions of production or transmission55% rewritten
- 03We have significant customer concentration, with a limited number of customers accounting for a substantial portion of our revenues56% rewritten
- 04Our projects are exposed to the risks inherent in the construction and operation of renewable energy projects, such as breakdowns, manufacturing defects, extreme weather, natural disasters, terrorist attacks and sabotage. We are also exposed to environmental risks22% rewritten
- 05There are a number of other companies operating in the renewable energy and waste-to-energy markets. These include other renewable energy companies and service or equipment providers, consultants, managers and strategic investors
- 06Our success depends, in part, on technological innovation to stay ahead of market competitors55% rewritten
- 07Our use and enjoyment of real property rights for our projects may be adversely affected by the rights of lienholders and leaseholders that are superior to those of the grantors of those real property rights to our projects29% rewritten
- 08We may not be able to obtain long-term contracts for the sale of power produced by our projects on favorable terms and we may not meet certain milestones and other performance criteria under existing PPAs
Business Strategy Risks
- 09Our commercial success depends on our ability to identify, acquire, develop and operate individual renewable energy projects, as well as our ability to maintain and expand production at our current projects26% rewritten
- 10difficulties in identifying, obtaining and permitting suitable sites for new projects28% rewritten
- 11If there is not sufficient demand for renewable energy, or the associated Environmental Attributes, or if renewable energy projects do not develop or take longer to develop than we anticipate, we may be unable to achieve our investment objectives
- 12Our fuel supply agreements with site hosts have defined contractual periods, and we cannot assure you that we will be able to successfully extend these agreements at their historic revenue levels or at all
- 13Our agreements contain complex price adjustments, calculations and other terms based on gas price indices and other metrics, the interpretation of which could result in disputes with counterparties that could affect our results of operations and customer relationships
- 14In order to secure contracts for new projects, we typically face a long and variable development cycle that requires significant resource commitments and a long lead time before we realize revenues
- 15We plan to expand our business in part through developing RNG recovery projects at landfills and livestock farms, including our Turkey, North Carolina location, but we may not be successful60% rewritten
- 16Our dairy farm project has, and any future digester project will have, different economic models and risk profiles than our landfill facilities, and we may not be able to achieve the operating results we expect from these projects46% rewritten
- 17While we currently focus on converting methane into renewable energy, in the future we may decide to expand our strategy to include other types of projects. Any future energy projects may present unforeseen challenges and result in a competitive disadvantage relative to our more established competitors35% rewritten
- 18The profitability of our renewable fuel projects may be limited by our ability to dispense fuel to separate RINs and the volatility of the price of RINs65% rewritten
- 19Our revenues may be subject to the risk of fluctuations in commodity prices
- 20We are exposed to the risk of failing to meet our contractual commitments to sell RINs from our production
Regulatory Risks
- 21The reduction or elimination of governmental economic incentives for renewable energy projects or other related policies could adversely affect our business, financial condition and results of operation57% rewritten
- 22We may be unable to obtain, modify or maintain the regulatory permits, approvals and consents required to construct and operate our projects24% rewritten
- 23Negative attitudes toward renewable energy projects from the U.S. government, other lawmakers and regulators, and activists could adversely affect our business, financial condition and results of operations76% rewritten
- 24Revenue from any projects we complete may be adversely affected if there is a decline in public acceptance or support of renewable energy, or regulatory agencies, local communities, or other third parties delay, prevent, or increase the cost of constructing and operating our projects78% rewritten
- 25solely on the condition that we carry out certain corrective measures to the proposed project. Opposition to our projects’ requests for permits or successful challenges or appeals to permits issued for our projects could adversely affect our operating plansNew
- 26Existing regulations and policies, and future changes to these regulations and policies, may present technical, regulatory and economic barriers to the generation, purchase and use of renewable energy, and may adversely affect the market for credits associated with the production of renewable energy30% rewritten
- 27In order to benefit from RINs and LCFS credits, our RNG projects are required to be registered and are subject to regulatory audit
- 28Our business is subject to the risk of extreme or changing weather patterns35% rewritten
Cybersecurity and Information Technology Risks
- 29A failure of our IT and data security infrastructure could have a material adverse effect on our business and operations
- 30Our business could be negatively affected by security threats, including cybersecurity threats and other disruptions32% rewritten
- 31Failure of third parties to manufacture quality products or provide reliable services in a timely manner could cause delays in developing and operating our projects, which could damage our reputation, adversely affect our partner relationships or adversely affect our growth
- 32Our projects rely on interconnections with and access to electric distribution and transmission facilities and gas transportation pipelines that are owned and operated by third parties, and as a result, are exposed to risks related to such facilities’ development and operational curtailment risks
- 33We are dependent upon our relationships with Waste Management and Republic Services for the operation and maintenance of landfills on which several of our RNG and Renewable Electricity projects operate27% rewritten
- 34Our senior credit facility may not be sufficient to meet our financial needs and contains financial and operating restrictions that may limit our business activities and our access to other forms of credit68% rewritten
- 35minimum Consolidated EBITDA (as defined in the Credit Agreement) of at least $10.0 millionNew
- 36We may be required to write-off or impair capitalized costs or intangible assets in the future or we may incur restructuring costs or other charges, each of which would harm our earnings31% rewritten
- 37We are in our last year of being an emerging growth company and will soon be required to comply with certain requirements that apply to other public companies65% rewritten
- 38If we identify material weaknesses in the future or otherwise fail to maintain an effective system of internal controls, we may be unable to accurately or timely report our financial condition or results of operations, which may adversely affect our business55% rewritten
Common Stock Risks
- 39Our shares of common stock may trade on more than one market and this may result in price variations
- 40Future sales of our common stock in the public market could cause the market price of our common stock to decline67% rewritten
- 41We are a “controlled company” within the meaning of the Nasdaq rules and, as a result, qualify for, and intend to rely on, exemptions and relief from certain governance requirements
- 42a compensation committee that is composed entirely of independent directors; and
- 43The concentration of our capital stock ownership may limit our stockholders’ ability to influence corporate matters and may involve other risks
- 44Certain of our directors reside outside of the United States and it may be difficult to enforce judgments against them in the United States
- 45If securities or industry analysts do not publish research or publish inaccurate or unfavorable research about our business, our share price and trading volume could decline
- 46We are highly dependent on our senior management team and other highly skilled personnel, and if we are not successful in attracting or retaining highly qualified personnel, we may not be able to successfully implement our business strategy
Other Montauk Renewables 10-Ks
- FY2024 10-K risk factors54 risks
Revenue heavily depends on a few major landfill sites and customers like Valero and ExxonMobil. Operations are exposed to volatile RIN prices, regulatory changes, and key third-party partnerships.