Summary
Management framed the quarter around disciplined execution, affordability and contracted industrial growth, while highlighting regulatory milestones and an uncertain holding-company outcome.
- The 1.7 GW data-center pipeline is upside to guidance, with some related transmission investment beyond 2030.
- The new large-load tariff provides a clearer cost-allocation framework; its 2026 earnings benefit is included but unquantified.
- Management emphasized flexibility in the coming multi-year rate plan and a bridge mechanism for 2028–2029.
Guidance
- $3.532026 diluted EPS $3.53
- 5%Long-term earnings and dividend growth 5% to 7%
- 1.5%2026 weather-adjusted load growth 1.5% to 2.5%
- 10%Large-customer capacity growth approximately 10% annually through 2030
- 4.8%2027 rate case overall increase approximately 4.8%, effective July 1, 2027
- 3.9%2027 rate case residential increase approximately 3.9%, effective July 1, 2027
- 2.4%Annual update tariff customer price reduction approximately 2.4%, beginning January 1
- 2025 renewable RFP contracts expected by early 2027, subject to negotiations and approvals
What analysts pressed on
- 01Large-load investment needs: management said the 1.7 GW pipeline is outside guidance and excluded additional generation and some transmission costs.
- 02Multi-year rate plan mechanisms: management said a proposed bridge would address inflation and costs in 2028–2029, while plan flexibility remains key.
- 03Wildfire legislation: management cited an Oregon PUC study expected in early fall and ongoing stakeholder discussions, without specifying legislative proposals.
- 04Holding-company settlement and timing: management cited alignment on many conditions but a remaining customer-benefit bid-ask spread; an extension has not been indicated.
- 05Affordability and rate case: management attributed lower residential increases partly to the large-load tariff and projected a 2.4% energy-cost reduction.
- 06Large-load tariff earnings contribution: management said the benefit is modest and included in guidance, but declined to quantify it.
Notable disclosures
- 1.7 GW of additional data-center pipeline is outside guidance, and some transmission needs fall beyond 2030.
- 10%Approximately 10% annual large-customer capacity growth through 2030 reflects named, contracted customers with facilities built or under construction.
- $25M$25 million in cost-management benefits were achieved, with some included in the upcoming rate case.
- The large-load tariff’s 2026 earnings contribution is described as modest, with no amount disclosed.
Risks raised
- The holding-company proceeding could end in a commission decision rather than settlement; management has not seen signs of delay.
- The 1.7 GW pipeline remains outside guidance, and its generation requirements are not included in forecasts.
- The Reliability Contingency Event mechanism expired, while broader power-cost reform remains unresolved.
- Some transmission investment associated with data-center growth is not included in the forecast through 2030.
Tone: Positive 0.58
Management cited solid execution, contracted load growth and cost savings, tempered by regulatory uncertainty and unquantified benefits from major catalysts.
Who spoke
Company
- Erin SchwartzInvestor Relations
- Maria PopePresident and CEO
- Joe TrpikChief Financial Officer
Analysts
- Unidentified AnalystAnalyst, Wells Fargo Securities
- Sophie KarpAnalyst, KeyBanc
- Aidan KellyAnalyst, JPMorgan
- Anthony CrowdellAnalyst, Mizuho
- Paul FremontAnalyst, Ladenburg Thalman & Company
- Travis MillerAnalyst, Morningstar
Full transcript
Analyst questions are marked with a bar. Timestamps are into the recording.
Prepared remarks
Good morning, everyone, and welcome to today's conference call with Portland General Electric /or/. Today is Friday, July 31st, 2026. This call is being recorded and all lines have been placed on mute to prevent background noise. After the speaker's remarks, there will be a question and answer period. If you would like to ask a question during this time, press star, than the numbers 1-1 on your telephone keypad. To withdraw your question, please press star 1-1 again. If you do intend to ask a question, please avoid the use of speaker phones.
Erin SchwartzInvestor Relations
For opening remarks, I will turn the conference call over to Portland General Electric /or/ Senior Manager of Investor Relations, Erin Schwartz. Please go ahead. Thank you, DG. Good morning, everyone, and thank you for joining us today. Before we begin, I would like to remind you that we issued a press release this morning and have prepared a presentation to supplement our discussion, which we will be referencing throughout the call.
The press release and slides are available on our website at investors. portlandgeneral. com. Referring to slide two, some of our remarks this morning will constitute forward-looking statements. We caution you that such statements involve inherent risks and uncertainties, and actual results may differ materially from our expectations. For a description of some of the factors that could cause actual results to differ materially, please refer to our press release and our most recent forms 10-K and 10-Q, which are available on our website.
Turning to slide three, leading our discussion today are Maria Pope, President and CEO, and Joe Terpik, Senior Vice President of Finance and CFO. Following their prepared remarks, we will open the line for your questions. Now, I will turn things over to Maria.
Maria PopePresident and CEO
Thank you, Erin, and good morning, everyone. We appreciate you joining us today. The second quarter was marked by continued execution across our strategic priorities. Strong industrial demand growth of 11% when compared to second quarter of last year. Advancement of key regulatory proceedings, disciplined cost management, and continued progress on resource planning. Beginning with slide four, I'll speak to our financial results and key drivers. For the second quarter, we reported GAAP net income of $68 million or $0.59 per diluted share and non-GAAP net income of $74 million or $0.64 per diluted share.
Our non-GAAP results exclude business transformation, optimization, and acquisition-related expenses, which are not reflective of ongoing operational performance. These costs relate to the holding company formation, the pending Washington acquisition, and our customer affordability work. These results were in line with our expectation for the quarter and reflect strong execution. As a result, we are reaffirming our full-year earnings guidance of $3.53 per diluted share, and our long-term earnings and dividend growth guidance of 5% to 7%.
Turning to slide 5 for updates on our five strategic priorities. First, industrial demand growth remains an important element of our long-term outlook. Today, we serve 12 different data center customers, which make up approximately one-third of our total industrial usage. Total industrial load growth was approximately 10% compounded annually over the last five years. We continue to see strong demand from technology, semiconductor, and data center customers with approximately 10% compadent annual growth expected through 2030.
This outlook is supported by customers who are under contract and whom are already energized or actively advancing construction and facility development in our service area. Second, affordability remains a national focus. We've taken proactive steps to address customer cost pressures, mitigate stranded asset cost risk, and enable growth that supports the long-term strength of our communities and continued economic development. In Q2, the OPUC issued a final order approving PGE's new large load tariff, effective in July, raising average prices approximately 30% for data centers, while lowering rates for all other customers and capping several years of legislative and regulatory work.
This important framework aligns infrastructure costs on an ongoing basis to customers driving new system investments, while helping reduce costs for residential and small business customers. The tariff also creates greater certainty for large load customers by providing a clear pricing framework, which supports investment decisions and continued economic development across our region. In addition to the changes implemented with our large load tariff, we continue to focus on operating costs and executing across our financial and operational priorities, which Jill will cover in more detail in a minute.
Third, we're advancing our 2025 renewable RFP. During the quarter, the OPC acknowledged the shortlist, marking an important milestone in the procurement process. The shortlist includes a diverse mix of wind, solar, battery storage, and hybrid resources, with both purchase power and company-owned structures under consideration. consideration. We are now moving into commercial negotiations and expect to execute contracts by early 2027, subject to final negotiations and approvals.
Fourth, our year-round wildfire mitigation work remains on track. We continue executing the actions identified in our 2026 through 2028 wildfire mitigation plan and remained engaged with policymakers and stakeholders regarding long-term wildfire policy discussions. Across Oregon, there are several active wildfires, and we appreciate the significant actions that first responders and local communities are taking. None of these wildfires are in PGE's service territory. And fifth, next week we will file our 2027 general rate case. As proposed, the case would result in approximately 4.8% overall increase relative to currently approved prices effective July 1, 2027, with residential customers seeking an approximately 3.9% increase.
The residential increase would have been higher if not but for the large load tariff. The rate case increase is expected to be partially offset by lower net variable power costs, which are addressed separately to the annual update cost tariff and are currently forecast to reduce customer prices by approximately 2.4% beginning on January 1st. The filing is based on a proposed 50% debt, 50% equity capital structure, and a 9.75% return on equity.
It reflects a balanced approach that supports continued investment in reliability, resiliency, and infrastructure, needed to meet growing customer demand while maintaining affordability and delivering the financial foundation necessary to serve customers safely and effectively over the long term. In parallel, we continue to advance our proposed holding company structure. We expect a final order at the end of August. The proposed structure will enhance financing flexibility and support our ability to invest in clean energy and meet significant customer and infrastructure needs over time.
Lastly, our teams remain focused on the regulatory work to obtain approvals for the Washington acquisition and continue to target a mid-2027 closing. As we move to the second half of 2026, we remain focused on delivering safe, reliable, and affordable service while advancing clean energy investments, our expansion into Washington, and completing the formation of the holding company. At the same time, we are operating to our plan and executing on actions to deliver on shareholder and customer commitments.
With that, I'll turn things over to Joe.
Joe TrpikChief Financial Officer
Thank you. Thank you, Maria, and good morning, everyone. Turning to slide six, our second quarter results were consistent with our guidance and reflect solid execution across the business, beginning with low trends year over year. Total retail energy deliveries increased 3.9% compared to the second quarter of 2025 on a nominal basis, and we're up 2.7% weather adjusted. As Maria mentioned, we continue to see strong demand from our technology semiconductor and data center customers with approximately 10% annual large customer capacity growth expected through 2030.
Industrial demand remained a key driver in the second quarter, increasing 11.2% year-over-year, reflecting continued demand from high-tech and data center customers. residential deliveries increased 1.3% on a nominal basis and were down 1.4% on a weather adjusted basis while commercial deliveries decreased 2 nominally and we down 2 weather adjusted Overall weather adjusted load across customer classes was largely consistent with our expectations Therefore, we are reaffirming our 2026 weather adjusted load growth guidance of 1.5% to 2.5%. Now we'll cover the primary year-over-year earnings drivers for the quarter. A decrease from power costs of $0.18 primarily driven by expected entry-year timing of revenue collection and power cost recognition.
We experienced a $0.22 increase in retail revenues, including a $0.10 increase from industrial demand, a $0.12 increase from additional cost recovery reflecting the seaside battery asset included in customer rates beginning in November 2025, and the distribution system planning recovery that began in April of 2026. Note that there was not a meaningful impact to our revenues from changes in residential or commercial customer usage over the year.
A $0.12 decrease from other capital and financing costs in support of our ongoing rate-based investments made up of $0.07 from higher depreciation and amortization, $0.03 from dilution, and $0.02 of additional interest expense. A $0.06 increase from O&M reflecting strong cost management and productivity improvements across the organization. On the slide 7 for our five-year capital forecast, which includes the 2026 and 2027 spend from the incoming 2023 RFP, I will note that this view does not contemplate CapEx from the 2025 RFP or the Washington acquisition, which, as Maria noted, are progressing as expected.
On the slide 8 for financing, we remain well-positioned. We have completed the majority of our 2026 financing activity providing clear visibility to our funding needs for the year, and this included $550 million equity issued under a forward sale, a $500 million ATM facility to further support the equity needs, a $350 million 24-month term loan satisfying our 2026 financing needs, and a $680 million delayed-drawed term loan related to the Washington acquisition available until specific acquisition milestones are achieved and maturing 364 days after funding.
And our investment-grade credit ratings remain unchanged. In July, the Board of Directors declared a quarterly common dividend of $0.55.125 per share, representing an increase of 5% on an annualized basis. We remain committed to paying a competitive dividend in line with our 60% to 70% payout target while balancing overall financing needs. Our plan focuses on maintaining strong operating cash flows while supporting continued investment in customer-focused capital projects, all while advancing us towards our authorized capital structure.
As we look to the second half of the year, we have a clear path to deliver on our guidance. We are providing quarterly guidance as the shape of our earnings is different than it has been in prior years.
First, we expect improved power costs over the remainder of 2026, helping offset the first half timing headwind. Second, in Q4 2025, the weather detriment is not expected to recur, with our 2026 forecast assuming normal weather.
Third, we expect margin improvement from the new large load tariff approved earlier this year. Fourth, we expect continued increased regulatory recovery, including the seaside and DSP alternative recovery mechanisms. And finally, we are executing management actions across operating and power costs to support earnings through the remainder of the year. We remain focused on safe, reliable, and efficient operations, advancing our strategic priorities, and delivering value for our customers, communities, and shareholders.
And now, operator, we are ready for questions.
Questions and answers
Thank you. As a reminder to ask a question, please press star 11 on your telephone and wait for your name to be announced. To withdraw your question, please press star 11 again. Please stand by while we compile the Q&A roster. And our first question comes from Julian Mullen-Smith of Jeffries. Your line is open. Morning, Julian.
Unidentified AnalystAnalyst
Hi, good morning. It's Brian Russo on for Julian. Good morning, Brian. Just first, if you could comment on the slide presentation, you have 1.7 gigawatts of additional data center pipeline. What kind of investment would be needed to support that? Is it generation and is it part of the 25 RFP? I just want to understand if that's like another bucket of potential growth investments for you guys.
Maria PopePresident and CEO
Sure. First of all, let me give you a little bit of background on the 1.7 gigawatts. The investments are in a number of different counties across our service territory, and the vast majority of that represents projects that are already in the permitting process. Many projects already have land ownership and are progressing really nicely. The 1.7 gigawatts will also be under the UM2377, which enables growth, pays for growth, it's like what we like to say, or our peak growth modifier and the most recent higher customer prices for data centers. But we have not included any of the additional generation. And you can see some transmission investments in our forecast, but not all of them. Some of them are beyond the 2030 time period.
Okay, great. And then just on the upcoming multi-year rate plan filing, looking ahead to the framework, Are there any key areas to focus on in terms of the mechanisms to help you maintain that just inherent lag, which I think is you're trying to close that gap to 50 basis points on the structural side? Just wondering what we might expect in terms of proactive mechanics in that MYRP filing.
Morning, Brian. I mean, you know, the multi-year framework, considering that it lists out for five years, right, our focus will be making sure it has flexibility for us to operate the business as expected and to be able to adapt to change. So, you know, but before we get to the multi-year, right, the way I focus on this is we have the general rate case that's here that will cover a period of time. And then we're proposing a bridge mechanism to get us to the multi-year because the multi-year rate would not be filed until 29 that would have rates effective in 30. So we're focused on this GRC, which would have rates effective July of next year, and then a bridge mechanism that would bridge 28 and 29.
And so starting with the bridge mechanism, you know, the design here is to be able to address inflation and cost between these full GRC type cases. And then to the multi-year, as I said, it's really about being able to balance and make sure that we can adapt. Considering it's five years, you know, there's an amount of uncertainty in that that will occur. So having the flexibility to balance and adapt will be key for us.
Okay, great. And then just lastly, on wildfire legislation, as we, you know, quickly approach the 2027 legislature session, you know, what's going to be like the key focus for you or how you are preparing for that, you know, to make some constructive steps in the upcoming session? Sure. So it's a great question. And we will continue the discussions that we've been having over the last couple of years with a variety of stakeholders. One thing I would note that's really constructive and an improvement this year is the Oregon Public Utility Commission's work.
They've hired Boston Consulting Group to do a study on wildfire and, obviously, utilities. And we look forward to the results of that report probably in the early fall time period and are very encouraged with that next good step, as well as working with stakeholders across the state and key customers as well.
Great. Thank you very much.
Thank you. Thank you. And our next question comes from Char Perez of Wells Fargo Securities. Your line is open.
Unidentified AnalystAnalyst, Wells Fargo Securities
Morning, guys. Good morning. Morning, Maria. Ray, just on the Salem Data Center, I guess since the state's pullback only affects kind of the state-owned portion of the site, not the private land, does that kind of change how you think about the 1.6 gig large load queue at all? Should we expect that to convert at the pace you got it to or some haircut the right way to think about it? Thanks.
Maria PopePresident and CEO
Sure. So first of all, the 1.7 is not in our guidance. It would be in addition and upside to our guidance. And just for those of you who are not tracking everything that's taken place with regards to the data centers in Oregon, for the Salem region, one of our large customers had anticipated purchasing some state land, And the governor will be reviewing that sale and has not made any final determination at this point in time. That is just a portion of the land that they own, over planning on owning. And the bulk of their investment would actually be on non-state land.
In addition, there has been some discussion in Hillsborough on data center moratorium. and most of our customers that are not in our forecast but that we are working with with additional upside are actually already in the existing permitting process and grandfathers. Got it. Okay, that's helpful. It clears up some confusion this morning. And then just with the whole co process now kind of getting to the finish line I guess how are you thinking about maybe updating the street and what it means to the current plan including maybe the balance sheet EPS financing flexibility I mean it obviously a creative so how should we think about a plan update, or do you want to wait for other items to kind of play out, you know, like the Washington acquisition, Seaside, et cetera?
Thanks. Yeah, morning, Shari. Yeah, we will give as As much of an update, as this process resolves itself, we will give an update how we can. But you're right, Char. I mean, we have multiple growth and earnings catalysts that sit in front of us that would have an interplay here. So any type of guidance we give will be somewhat of a flexible view of the world. We don't want to front run the other processes that are out here. I mean, I agree with you. There's that, you know, having a holding company to, you know, align us with where the industry is and give us, you know, the flexibility to drive benefits for our customers. And that further, I think, is important.
And we'll just balance how we guide this as these items in front of us are critical to its true, you know, its true ability to drive value.
Okay, got it. Thanks, Joe. Appreciate that. Thanks, Maria.
Thank you. Thank you. And our next question comes from Sophie Karp of KeyBank. Your line is open.
Sophie KarpAnalyst, KeyBanc
Hi, and good morning. Thank you for taking my question. So I wanted to ask you, with the large load ramp that you may be seeing, is there a scenario where this incremental load and associated cash flow offsets some of your financing needs? and is there a line of sight to that or too early to speculate?
Maria PopePresident and CEO
Yeah, that's a great question. It's probably too early to speculate, but we're really pleased with the cooperation we had from all of our customers, the partnership with the PUC, the legislative changes that were made that resulted in a 30% customer price increase for data centers effective in early July, and the resulting impact of that as we move forward through the general rate case, as well as future years. It will be very helpful as we move forward to our overall P&L.
Sophie KarpAnalyst, KeyBanc
Yeah, yeah, for sure. Okay, and then on the whole goal outcome, yes, the hearings have concluded, as I understand. We heard the party's positions, so everybody's kind of said their piece. Like, at this point, what do you see as the most likely outcome, and how would you frame the positive impact from it, you know, as you see today versus maybe where you started?
Maria PopePresident and CEO
Sure. So, first of all, it has been a process that's gone on for over a year, and we've had many discussions, and we hope to conclude by the end of August. The most recent discussions that you're referring to were some concluding public testimony where people pretty much reiterated their same and sort of from the beginning public statements. There have been a number of settlement conferences. Some of these are confidential, and we are really pleased with being able to come to an alignment on a number of important governance conditions, as well as customer benefits and other items. The case overall has great merit.
Much of what we have proposed and agreed upon to is not just similar to Northwest Natural and other utilities' concluded results, but in some instances absolutely identical in the types of conditions and aligned with the precedents that have been set.
All right.
Sophie KarpAnalyst, KeyBanc
Thank you so much, Sophie. Thank you, Sophie.
Thank you. And our next question comes from Aidan Kelly of JPMorgan. Your line is open.
Aidan KellyAnalyst, JPMorgan
Hey, good morning. Thanks for the time today.
Maria PopePresident and CEO
Good morning. If I could, maybe just picking up again on the Holdco front, just how would you kind of characterize the delta between, you know, Portland and key stakeholders at this point? And just, like, do you see any risks of the proceeding getting further delayed or punted into next year at all, or you feel firm on that August 25th kind of deadline?
Joe TrpikChief Financial Officer
Good morning. So, you know, I think as we are working backwards here, I mean, I think all the key facts and all the key dialogue are really laid out pretty cleanly in the testimony. So I think, you know, the facts are there to be considered, you know, pretty cleanly. I think when you talk to Delta here, which obviously varies by parties, but there's, you know, there's pretty good alignment as it relates to a lot of the conditions that would fall through here on the case. I mean, there's always a bit of a delta on what I'll call the bid-ask spread on what is the benefit to the customers or what is the rate credit to the customer.
But I mean, I think fundamentally as to the conditions, we're relatively aligned. So, I mean, I think it comes down to maybe some of the finer points on the conditions and then it's really the bid-ask spread here is really where we sit. You can see that cleanly in some of the And the testimony from some of the parties, you'll notice that we're just really relatively aligned and it comes down to dollars.
So we're pretty satisfied with the way we've laid out the case. We think it's pretty clear on the benefits that are available to the customers. We're pretty clear on it is not a, it's obviously as you all know, a pretty consistent practice to have across the industry. So we think that, I'll close with the facts are there to have them decide the case. We haven't seen any indicators yet that it would extend, but obviously we're waiting to see just like you would be.
Aidan KellyAnalyst, JPMorgan
Thanks. Yeah, appreciate the color there. Maybe if I could just shift to the, you know, GRC backdrop. I appreciate you guys kind of laying out your thoughts and goals there. I guess just zooming out, how do you kind of rate the current affordability backdrop versus the recent past, you know, and your kind of key, I guess, items in the proposal that kind of drive that 4.8% net increase? And, you know, maybe if you could tee that up, kind of compare it to prior GRC cycles, Just any thoughts kind of going into this filing next week.
Maria PopePresident and CEO
Sure. So first of all, I want to note that we have not filed a general rate case in two and a half years. So we take affordability very seriously, and we have been working diligently and effectively on our operating costs through our customer affordability commitments. And this rate case reflects the benefits for residential small business and other customers from the most recent new low tariff, UM-2377, which, as I noted, raised data center prices by about 30%. Data center prices will go up significantly more than the average of 4.8. And residential customers are lower at about 3.9. We think that we have really got a lot to address affordability. When you factor in at January 1st our proposal to reduce energy costs through the annual update tariff by 2.4%, it's really just a couple of percent increase for our customers as they move forward.
And we have also reflected really important infrastructure investments, some smart grid and grid-enhancing technology investments, as well as reflected things that customers, particularly on the residential, small commercial side, value and have been fairly vocal about. So we look forward to proceeding over the next year through discussions collaboratively with all stakeholders in the commission.
Aidan KellyAnalyst, JPMorgan
Thanks, Mary. I appreciate the call there. Sorry, there's just one more question I keep getting asked. Is it possible for you guys to still settle the hold code today? just like yes or no?
Maria PopePresident and CEO
Yeah, absolutely. As you know, we have a record of settling most of our discussions. You know, it's August or going into August, and there's people on vacation and others, so my hope is that we do settle quickly. But the date is August 25th, so we may end up in a commission decision, and we look forward to continuing the conversations.
Great. Appreciate the time today. I'll leave it there.
Aidan KellyAnalyst, JPMorgan
Thank you. Take care.
Thank you. Thank you. And our next question comes from Anthony Crowdel of Mizuho. Your line is open.
Anthony CrowdellAnalyst, Mizuho
Hey, good morning, team. If I could just jump on the last question to start off. Any chance that it seems that there's, and hopefully I'm not putting words in your mouth, it seems that there's active settlement discussions going on. Is there any chance the commission, actually I think Sophie asked how hard is that August 25th deadline, is there any chance that they would move that out knowing that there's active settlement discussions?
Joe TrpikChief Financial Officer
Yeah. You know, I guess, Anthony, Joe Terpik, so, you know, one, we haven't heard any dialogue to that. And, you know, to your comment on the settlement dialogue, the settlement dialogues are always open and part of the process. So this, you know, this type of dialogue and settlement discussion is no different than other cases. so I'm not sure that it would be some indicator that says to prolong the hearings.
Anthony CrowdellAnalyst, Mizuho
And, again, are there settlement discussions going on with all the major parties, or are you kind of focused on maybe a smaller group of interveners?
Joe TrpikChief Financial Officer
Yeah, and considering on how we're in the middle of a case here, there are discussions that are out there. I think any further detail would really front-run some items. So they're just open discussions that are out there.
Anthony CrowdellAnalyst, Mizuho
Great. And then if I and I apologize, I'm just getting things confused. I believe maybe earlier this year you guys had pulled a transmission case not to confuse a holding the holding company approval with the transmission rate case. the holding company, you know, for full approval still pending, and the thoughts of maybe the timing of why file the general Ray case now prior to maybe closing the transmission I sorry the holding company case up It seems that just curious on you pulled one case because you really wanted to focus beyond the holding company structure and now possibly going in and file another case prior to the holding company structure.
Maria PopePresident and CEO
Sure. So, first of all, thank you for the question. And we do remain focused long-term on the transmission, but knowing that there was a considerable amount of work in front of the commission, we really narrowed to the holding company, which includes the Washington acquisition, of course, and have had quite a few discussions with parties with regards to the general rate case and felt that this was an optimal time. As you may recall, led by the Citizens Utility Board and some others, we worked with parties to come up with something, some legislation, in addition to the Power Act, which resulted in larger customer price increases for data centers, but for not having rate increases go in during certain times of the year.
And so, given the discussions that we've had so far with parties on the general rate case, we really felt that filing in August would be workable for everyone. And since we've not have had a rate case for two and a half years, timely.
Joe TrpikChief Financial Officer
And, Anthony, just a reminder, obviously, the transco filing was a structural filing here and didn't really impact how or when we collect rates on the transmission assets. Those have worked themselves through the same process that they did before. So any of that timing or pulling of things doesn't have anything to do with rate recovery. It was solely structured.
Anthony CrowdellAnalyst, Mizuho
Got it. So just to make sure I have the sequence right, general rate case filing, expectation, holding company formation, hopefully later in the month.
Joe TrpikChief Financial Officer
That is correct.
Anthony CrowdellAnalyst, Mizuho
Thanks for taking my questions. Thank you.
Thank you. And our next question comes from Greg Orill of UBS. Your line is open.
Unidentified AnalystAnalyst, UBS
Yeah, thank you. So just regarding the reliability contingency structure, just maybe you could talk to, you know, what that, what the prospects are for continuing that and, you know, how that was viewed by the commission. Why did they decide not to, you know, continue to move forward with that? And then maybe also just on the O&M reduction plan, if there's any sort of update on that and sort of the prospects going forward.
Thank you. Given a success.
Maria PopePresident and CEO
Good morning. So the Reliability Contingency Event, or RCE, was a mechanism that was afforded us in the last case that had a two-year period, which expired here. You know, that mechanism we felt worked quite effectively here. You know, we had an unusual ice storm and had some significant deviations in cost, and it pretty effectively captured those differences. You know, it was put in initially with a two-year timeframe with the expectation that we would ultimately align to broader power cost reform. That has not occurred as of yet, but the RCE did expire. I think, you know, the staff at least viewed it as an experiment. You know, it worked the way it's worked, and they ultimately like to get away from that type of mechanism and just, you know, ultimately address broader reform at some point in time in the future.
So, you know, this is, you know, that is sort of an expired item that we're not subject to currently. You know, obviously, we like that type of mechanism. Joe should go on and talk to your question about O&M, but I do want to just comment that we are aligned with staff and with policymakers across the state on the impacts of extreme weather and whether that is impacting customer energy usage, power costs, and we need to look more holistically at all of these things combined as we move forward.
Joe, do you want to cover his question on O&M?
Joe TrpikChief Financial Officer
Yeah, thanks for asking on the O&M. I'm pretty happy with where we sit on the O&M side. As you may recall, we entered into this last year. We entered into a cost management program here, yielded about $25 million in benefits. In fact, those benefits are part included in the general rate case to help mitigate what costs, considering it has been two and a half years since we filed the case.
And we'll continue to proceed with the program. You can see some of the results this year as they fall through the earnings waterfall year to date. The company has been pretty committed to not just squeezing to find savings, but to transform and we find ourselves, you know, we've probably got another couple years of this left, but I think to date you would score the effort as successful and very aligned with our expectations and very aligned with how it ties into our longer-term strategy.
Unidentified AnalystAnalyst, UBS
Okay, thanks for the updates.
Thank you. And our next question comes from Paul Fremont of Ladenburg Thalman & Company. Your line is open.
Paul FremontAnalyst, Ladenburg Thalman & Company
Hey, thank you guys very much. I guess my first question is, I think earlier in the year and maybe towards the end of last year, you were pretty optimistic about being able to sell the whole code case. do you feel less optimistic at this point, or are you still in the camp that it's highly probable that you will settle the case?
Maria PopePresident and CEO
Sure. So we were optimistic then, and we are optimistic now. We have a strong case, good benefits for customers, and the discussions are ongoing.
Paul FremontAnalyst, Ladenburg Thalman & Company
Great. And then I guess during oral arguments, some of the commissioners sort of asked whether there are alternative mechanisms to double leverage to fund capital spending in the future. I think they mentioned securitization. Sort of any thoughts along those lines in terms of what alternatives might be available to the company?
Maria PopePresident and CEO
So I don't think we want to be front running the process. The discussion that took place in oral arguments was as expected and one part of the process. But clearly it's important to the company to have the flexibility afforded to the vast majority of utilities across the country in terms of having a holding company structure.
Joe TrpikChief Financial Officer
Paul, can I just add, you know, I mean, this, the focus on the holding company was about this is the structure that can yield the greatest benefits to the customers by a good distance and give us the tools that, you know, the one that gives us the most tools there. So there are always alternatives out there, but those alternatives will, you know, they can yield benefits, but they will not yield as meaningful to both, you know, the customer and design benefits as the structure that we propose.
Paul FremontAnalyst, Ladenburg Thalman & Company
Great. I think that's it for me. Thank you very much.
Thank you, Paul. Thank you. And our next question comes from Travis Miller of Morningstar. Your line is open.
Travis MillerAnalyst, Morningstar
Hello. Thank you. You answered most of my questions, but just a couple quick clarifying ones. What's the earnings impact from the large load tariff that you have in the guidance? And what was initially included in the guidance? Has that changed, though?
Joe TrpikChief Financial Officer
So, you know, initially in the guidance, obviously, we gave our broad guidance for the year. The large load tariff was not a proposed document, and there was nothing, you know, included. And, you know, as we've gone through the year and as the large load tariff, you know, we've incorporated the effects. We haven't to date quantified that, but we've incorporated the effects as a, you know, really as a balancing. As you know, we were reacting to some of the first quarter items. So there's a, you know, there's a modest amount of benefit that's layered in here for the year.
Maybe I'll just leave it at that.
Travis MillerAnalyst, Morningstar
Okay. And presumably that would carry over at least through the first half of next year, right? So it should be a little bump in growth all else equal. Okay. Okay. And then one other quick clarifying one. The 10% five-year CAGR you're talking about, or at least through 2030, with the new customers, is that the ramping of existing contracted customers? Or is there an assumption of some additional large load customers that you'll get in the next couple of years?
Joe TrpikChief Financial Officer
So, you know, what I feel makes our disclosure there a bit unique is these are contracted customers. These are customers who are already either have constructed facilities or facilities that are under construction currently. So this ramp is really about, you know, these contracted and constructed assets here for us, which I feel makes it a little different is we don't have – there is not a speculative queue here. I mean, you know, the opportunity port that we talked to earlier on this call, that 1.7, I guess, you know, Some of that could have a different level of certainty, but the ramp that we have at 10% is solid. They have names. They have locations. They have companies to them.
So, you know, we're pretty confident with the work that's laid out for the 10% ramp.
Travis MillerAnalyst, Morningstar
Perfect. And real quick, presumably those customers, at least most of them, would pay that large load tariff.
Joe TrpikChief Financial Officer
Yeah, those customers, the large load tariff is applicable to all customers once you meet certain megawatts. criteria, yes. And, you know, and they obviously, those parties were, you know, able to respond and then were engaged in the process that ultimately resulted in the large load tariff.
Travis MillerAnalyst, Morningstar
Okay. Great. Thanks so much.
Thank you very much. So, I think with that, we are finished and don't have any more questions. We want to thank everyone for your time today. We look forward to further conversations at conferences through the balance of the quarter and the fall. And thank you for your interest and Portland General Electric /or/. This concludes today's conference call. Thank you for participating, and you may now disconnect.
Other Portland General Electric earnings calls
- Q3 2026 earnings call
Management framed the quarter as disciplined execution amid unusually mild weather, while emphasizing that customer growth and the capital plan remain intact.
Oct 29, 2026Mildly positive0.25
About this transcript
The summary, guidance, analyst focus, and tone are automated and should be checked against the call before being relied on. Names and figures can be misheard. Listen to the replay.